Reported

Kitsilano developer seeks taller tower with hotel, cutting 64 homes

Millennium Development wants to revise an approved 20-storey rental tower at West 1st Avenue to 26 storeys with 99 hotel rooms, dropping the number of homes from 185 to 121.

Email

Reported. A news outlet found this. voche.me names the outlet and links its report. Read the original report on cityhallwatch.wordpress.com.

Illustration of a construction site with a tall tower under construction in a residential neighbourhood
Illustration made with AI for voche.me

A developer wants to revise an already-approved Kitsilano rental tower into a taller building with a hotel, dropping the total number of homes by 64. Residents can ask questions about the revised plan until December 1.

Millennium Development submitted a revised rezoning application in August 2026 for the site at 2158-2170 West 1st Avenue, near Kits Beach. The original application, approved unanimously by City Council in June 2025, was for a 20-storey, 185-unit rental building, with 34 of those units priced below market. The revised scheme, as reported by CityHallWatch, asks for 26 storeys (92 metres), 121 rental homes (97 at market price, 24 below market), and 99 hotel rooms on floors 6 to 16.

What the numbers show

The proposed building would be taller and denser than the approved version. The floor space ratio rises from 6.8 to 8.73, and the building gains six storeys and 27 metres in height. The hotel floors alone account for 77,611 square feet of the revised total floor area, according to the CityHallWatch review of the application materials.

The number of homes falls. The approved scheme had 185 units; the revised one has 121, a reduction of 64. Below-market units fall from 34 to 24, a reduction of 10.

The site's previous tenants were evicted on October 31, 2026, and demolition fencing went up the same day, CityHallWatch reports.

Context

The June 2025 public hearing on the original 20-storey rental tower drew 85 speakers and letters in opposition and 33 in support, according to CityHallWatch.

CityHallWatch notes that the site sits 750 metres north of the future Arbutus Station. It also notes that the application requests height and density beyond what the existing policy for the area allows, and that hotel use is not currently permitted on this site.

Public participation

The City opened an online question-and-answer period on November 18. Residents can submit questions on the ShapeYourCity platform (shapeyourcity.ca/2158-2170-w-1-ave-3) until December 1, 2026. Written comments can be submitted on the same platform after the Q&A closes. The City's rezoning planner for this application is Oskar Eriksson.

Questions this story answers

What does Millennium Development want to change at 2158-2170 West 1st Avenue in Kitsilano?

Millennium Development submitted a revised rezoning application in August 2026 to increase the approved 20-storey rental tower to 26 storeys (92 metres) and add 99 hotel rooms on levels 6 to 16, according to CityHallWatch. The original approval, granted in June 2025, was for a 20-storey, 185-unit rental building with no hotel.

How many homes would the revised proposal remove compared with the approved tower?

The revised proposal would have 121 rental homes, down from 185 in the approved scheme, a loss of 64 units. The number of below-market homes would also fall from 34 to 24, according to the CityHallWatch report on the application documents.

What was the floor area ratio in the original approval compared with the new proposal?

The approved scheme had a floor space ratio of 6.8. The revised proposal requests a floor space ratio of 8.73, a larger building overall despite having fewer homes, because the hotel portion occupies 77,611 square feet of the additional floor area, according to the application materials.

What happened to the people who lived in the building that previously stood on the site?

CityHallWatch reports that the last tenants were evicted from the existing building on October 31, 2026, and demolition fencing went up immediately after. The original 20-storey rental approval was granted in June 2025, and the developer began steps to clear the site within months of that approval.

Why did the previous application face opposition at a public hearing?

CityHallWatch reports that at the June 2025 public hearing for the original 20-storey rental tower, 85 speakers and letters opposed the project while 33 were in support. The hearing was for a purely residential rental tower; the new proposal adds a hotel component and reduces the number of homes by 64.

Will there be a public hearing for the revised proposal?

The City's materials state the application may be 'consistent with Official Development Plan' provisions, which under Vancouver Charter section 559.02(4) could allow it to proceed without a public hearing. The current process is an online question-and-answer period rather than a traditional in-person hearing.

When can residents ask questions about the revised proposal?

The online question-and-answer period on the ShapeYourCity platform (shapeyourcity.ca/2158-2170-w-1-ave-3) runs from November 18 to December 1, 2026. Written comments can be submitted on the same platform after the Q&A closes.

Who is the City's planning contact for this application?

The City's listed rezoning planner for this application is Oskar Eriksson, according to CityHallWatch. His phone number is 604-829-9270. Residents can also submit written questions and comments on the ShapeYourCity platform at shapeyourcity.ca/2158-2170-w-1-ave-3 until December 1, 2026.

Sources

The pages this story draws on. Open one to check a claim yourself.

  1. CityHallWatch: 2158-2170 W 1st Ave, Millennium's 26-storey revised rezoningcityhallwatch.wordpress.com
  2. ShapeYourCity: 2158-2170 W 1st Ave application pageshapeyourcity.ca

Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.

Topics

More from voche.me

CORRECTIONS

Report a problem on this page.

Tell the editors what is wrong and where the correct information can be checked. The page you are on is attached automatically.