Broadway Subway scheduled to open in fall 2027, two years past its first target
The Broadway Subway is now scheduled for passenger service in fall 2027, two years past its original late-2025 target. All trackwork is complete. Broadway between Cambie and Alberta streets will not fully reopen to vehicles until January 2027. CityHallWatch documented current conditions at three stations on November 21.
Long read. The subject the most local outlets covered that day, with the public record behind it. Every outlet and record is linked under the story. Read the original report on cityhallwatch.wordpress.com.

The Broadway Subway is now scheduled to open for passenger service in fall 2027, two years past the original late-2025 target, the Province of British Columbia confirmed in a September 2026 news release. CityHallWatch documented current conditions at three stations along the route on November 21.
All trackwork is complete. Test trains are running on the elevated guideway. The line is not open to passengers.
Budget and funding
The project has a total budget of nearly $3 billion. Canada contributes almost $897 million, BC contributes nearly $2 billion, and the City of Vancouver contributes $100.3 million, according to the September 2026 BC government news release.
As of a July 2026 project report cited by CityHallWatch, $2.258 billion of the $2.954 billion budget had been spent at that point. The original opening target was late 2025. The Province announced an early 2026 target in 2022. The line has since missed both.
What is finished
A September 2026 BC government news release confirmed all trackwork was complete at that time. CityHallWatch and broadwaysubway.ca both confirm test trains are now running on the elevated guideway as of November 2026. Station interiors are still being fitted out.
The BC government news release noted that traffic-deck removal and corridor restoration work was continuing at Broadway stations in September 2026. The team had finished removing the traffic deck at Broadway-City Hall Station in August 2026 and was installing utilities and restoring streets there. That work involves rebuilding the sidewalks, roadway surface, cycling infrastructure and planted areas that were removed when the tunnel was built from below.
The Broadway Subway is a 5.7-kilometre extension of the Millennium SkyTrain line from VCC-Clark Station west to Arbutus Street, with six new stations: Great Northern Way-Emily Carr, Mount Pleasant, Broadway-City Hall, Granville, South Granville, and Arbutus. Once open, broadwaysubway.ca says the trip from VCC-Clark to Arbutus will take 11 minutes. The line will connect the east end of the Broadway corridor to the intersection of Broadway and Arbutus Street, where riders can transfer to the 99 B-Line for points further west.
The six stations serve different parts of the Broadway corridor. Great Northern Way-Emily Carr serves the Emily Carr University of Art and Design campus and the growing False Creek Flats area. Mount Pleasant Station is at Broadway and Kingsway, one of the most congested intersections on the corridor. Broadway-City Hall places a SkyTrain stop at Vancouver City Hall for the first time.
Broadway street closure
Broadway between Cambie Street and Alberta Street will not fully reopen to vehicles until January 2027, broadwaysubway.ca says in its current-work section. The road work has displaced transit riders and drivers along the corridor since the main construction period began.
CityHallWatch photographed the corridor on November 21, 2026 and documented current conditions at the Thornton, Great Northern Way-Emily Carr, and Mount Pleasant station sites.
Thornton Street and the greenway
Thornton Street has been closed since April 12, 2021. CityHallWatch reported that street restoration on Thornton is planned for 2027, with no specific date yet set. A Central Valley Greenway detour sign installed during the closure still reads "fall of 2025" and was still in place as of November 21, 2026.
CityHallWatch noted that a small pedestrian path is now accessible along the west side of Thornton Street, an improvement for people on foot, though full street restoration remains more than a year away.
Businesses and the construction corridor
CityHallWatch documented the closure of Fable Diner near the Mount Pleasant Station site. The diner closed August 23, 2026, attributing the closure to the construction impacts on the surrounding block.
The months-long street closure on Broadway has affected businesses throughout the corridor, particularly near stations where large construction zones have restricted access.
The UBC extension
A further extension of the Broadway Subway from Arbutus Street west to the University of British Columbia campus is a separate, unbuilt project. CityHallWatch cited an estimate of $8 billion for the UBC extension. No construction date has been set for it.
For people who travel the Broadway corridor
Drivers who use Broadway between Cambie and Alberta streets can expect road work to continue through January 2027, when broadwaysubway.ca says full vehicle access will be restored.
Pedestrians near Thornton Street now have a small path along the west side, but full restoration of the street is not planned until 2027. No specific month has been given.
The Broadway Subway line will not open to passengers until fall 2027. TransLink and the Province have not announced the specific date within fall 2027 when service will start.
Riders who currently use the 99 B-Line bus along the Broadway corridor can follow the project at broadwaysubway.ca. The project's 24-hour construction information line is 1-844-815-6114.
A related long read published on this site on November 16 covers current construction details at station sites along the route, including photos from broadwaysubway.ca's most recent monthly reports.
Questions this story answers
When will the Broadway Subway open?
The Broadway Subway is scheduled to open for passenger service in fall 2027, according to a September 2026 BC government news release. The project's own website, broadwaysubway.ca, confirms the new line is opening in 2027. TransLink and the Province have not announced a specific date within fall 2027. The original target was late 2025.
When will Broadway reopen to vehicles?
Broadway between Cambie Street and Alberta Street is expected to fully reopen to vehicles in January 2027, according to broadwaysubway.ca's current-work page, which states that road work continues through January 2027. CityHallWatch documented the street closure as of November 21, 2026.
How much has the Broadway Subway cost so far?
As of a July 2026 project report cited by CityHallWatch, $2.258 billion of the $2.954 billion total budget had been spent. The project is funded by three levels of government: Canada contributes almost $897 million, BC contributes nearly $2 billion, and Vancouver contributes $100.3 million, according to a September 2026 BC government news release.
What is Thornton Street's status?
Thornton Street has been closed since April 12, 2021. CityHallWatch reported on November 21, 2026 that street restoration on Thornton is planned for 2027 with no specific date set. A Central Valley Greenway detour sign installed during the closure still reads 'fall of 2025' but was still in place as of November 2026.
Is the trackwork finished?
Yes. A September 2026 BC government news release confirmed that all trackwork was complete. Test trains are now operating on the elevated guideway, according to both CityHallWatch and broadwaysubway.ca. The line is not yet open to passengers.
What happened to Fable Diner near the Broadway Subway construction?
Fable Diner, located near the Mount Pleasant Station site, closed on August 23, 2026. CityHallWatch reported on November 21, 2026 that the diner attributed its closure to the impacts of Broadway Subway construction.
What is the Broadway Subway extension?
The Broadway Subway is a 5.7-kilometre extension of the Millennium SkyTrain line from VCC-Clark Station west to Arbutus Street, with six new stations. The project's own website says the trip from VCC-Clark to Arbutus will take 11 minutes once the line opens. It is funded by Canada, BC and the City of Vancouver, with a total budget of nearly $3 billion.
What is the UBC extension?
The UBC extension is a proposed further extension of the Broadway Subway from Arbutus Street west to the University of British Columbia campus. CityHallWatch cited an estimate of $8 billion for that extension on November 21, 2026. No construction date has been set for the UBC extension.
Sources
The pages this story draws on. Open one to check a claim yourself.
- Current Status of Broadway Subway, CityHallWatch, November 21, 2026cityhallwatch.wordpress.com
- Broadway Subway Current Work, broadwaysubway.cabroadwaysubway.ca
- Broadway Subway Project Overview, broadwaysubway.cabroadwaysubway.ca
- Broadway Subway scheduled to open fall 2027, BC Government news release, September 2026news.gov.bc.ca
Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.