The North Shore Wastewater Treatment Plant and what it means for your utility bill

A new regional treatment plant is the main reason District of North Vancouver utility rates are headed up 7.4% in 2027. Council votes on the rate on December 7.

Email

Long read. The subject the most local outlets covered that day, with the public record behind it. Every outlet and record is linked under the story. Read the original report on metrovancouver.org.

The District of North Vancouver's combined utility rate is heading for a 7.4% increase in 2027, and the main reason is a large wastewater treatment plant under construction on the North Shore. Council will vote on the rate on December 7, 2026.

The November 10, 2026 budget report from the District's Manager of Financial Planning and Reporting, Jaskaran Gill, names the North Shore Wastewater Treatment Plant as the primary driver of utility rate pressure, and warns that longer-term regional costs tied to it remain a significant financial risk beyond 2027.

What the plant is and why it is being built

Metro Vancouver is building the North Shore Wastewater Treatment Plant to replace the Lions Gate Wastewater Treatment Plant, which currently serves residents across the North Shore. Metro Vancouver's project page describes the Lions Gate facility as one of the last plants on the west coast of Canada and the United States to provide only primary wastewater treatment, meaning it removes solid material from sewage but does not treat it further.

The new plant will provide tertiary filtration treatment, a higher standard that removes more contaminants before water is released. Metro Vancouver's project page says the plant will serve over 300,000 residents and businesses in the District of North Vancouver, the City of North Vancouver, West Vancouver, the Sḵwx̱wú7mesh Úxwumixw (Squamish Nation) and the səlilwətaɬ (Tsleil-Waututh Nation).

The project has three parts: the new treatment plant itself, the First Narrows Pump Station and three kilometres of conveyance pipes connecting it to the system (completed in September 2022), and design work for eventually decommissioning the Lions Gate facility.

The construction timeline

Metro Vancouver's project page puts the primary construction period from 2025 to 2030. The Lions Gate plant will be decommissioned after 2030. Construction runs Monday to Friday from 7:00 am to 8:00 pm and Saturdays from 9:00 am to 5:00 pm, in line with District bylaws or variances the project has received.

The Federal and Provincial governments are providing joint funding of up to $405 million toward construction, according to Metro Vancouver's project page. The North Shore Local reported in April 2024 that Metro Vancouver's revised total project cost estimate, following a task force review, reached $3.86 billion.

The project history is significant for District residents. The original design-build contract with Acciona was terminated. Metro Vancouver and Acciona then went to court: the North Shore Local reported in April 2024 that Acciona filed legal action seeking over $250 million in damages, and Metro Vancouver countered with a $500 million claim, citing the costs of transitioning to a new contractor, repairing deficient design and construction, and completing the project. PCL serves as construction manager for early works and AECOM finalized the plant design, as the North Shore Local reported. The District's November 10, 2026 budget report refers to an Acciona settlement and says Metro Vancouver is updating its financial forecasts to reflect it. The report says there may be some near-term reduction in utility rate pressure as a result, though longer-term regional costs remain a significant risk. The report does not give a dollar amount for the settlement in that document.

What it means for utility bills

The 7.4% combined utility rate outlook in the District's budget report covers water supply, liquid waste and solid waste services. The North Shore Wastewater Treatment Plant is the main driver of the liquid waste component. Metro Vancouver charges the municipalities it serves for regional infrastructure costs, and those charges pass through to residents in their utility bills. The District has no direct control over those regional charges.

The budget report's cost-to-the-average-home table shows utility charges for a typical District townhouse at $2,222 in the 2026 budget. Under the 7.4% rate outlook, that figure would rise by $164, to $2,386, according to the report. These are preliminary figures subject to reconciliation when the utility rate recommendation goes to Council on December 7.

The report notes that wet-weather pricing and longer-term Metro Vancouver costs remain significant financial risks. The North Shore Wastewater Treatment Plant's construction runs to 2030, with the Lions Gate plant decommissioning costs following after that. Rate pressures from the plant are not expected to ease in the near term.

What the new Council committed to

The plant's cost was a central topic in the October 2026 election, and several of the people elected made specific commitments about it. All of these commitments are listed as not started on the promise tracker.

Councillor Lisa Muri committed to containing spending and reducing the property tax increase, naming the utility bill from the North Shore Wastewater Treatment Plant as the reason to hold the municipal tax portion down.

Councillor Jim Hanson pledged to speak out for a public inquiry into the plant and for accountability around it.

Councillor Jordan Back promised to push for transparency and accountability at Metro Vancouver, including a public inquiry into the plant, and to seek help from other levels of government to ease the cost for North Shore residents.

Councillor Daniel Anderson committed to fighting for a fair split of the plant's levies to ease the impact on North Vancouver households.

Councillor Catherine Pope wrote during the campaign that she has demanded answers on the plant since 2024 and will keep fighting for lower utility bills.

Mayor Mike Little's campaign commitments focused on keeping the District's budget on core services and business taxes in the lower half of the region. His tracker lists no specific commitment about the wastewater plant itself.

What comes next

The December 7, 2026 Council meeting will receive updated utility rate recommendations, including the household impact of each option. That meeting is separate from the November 23 budget vote on property taxes. The November 23 vote sets the planning direction for the 2027 property tax increase. The utility rate is a different bill, and the December 7 Council decision will determine how much residents pay for water and sewer services in 2027.

District residents who want to follow the December 7 decision can watch for the agenda on the District's document site at dnv.org, usually published the week before the meeting. The councillors' commitments on utility bills and Metro Vancouver are tracked at /bc/north-vancouver-district-2026/tracker.

Residents with questions about construction noise or disruption near the plant site can reach Metro Vancouver's project liaison at 604-639-9012.

Questions this story answers

What is the North Shore Wastewater Treatment Plant?

It is a new facility Metro Vancouver is building to treat wastewater for over 300,000 residents and businesses in the District of North Vancouver, the City of North Vancouver, West Vancouver, the Squamish Nation and the Tsleil-Waututh Nation. The plant will replace the Lions Gate Wastewater Treatment Plant, which provides only primary treatment. The new plant will provide tertiary filtration treatment, a higher standard. Metro Vancouver's project page describes it as one of the last plants on the west coast of Canada and the United States still running at the primary level only.

How much is the North Shore Wastewater Treatment Plant costing?

The Federal and Provincial governments are providing joint funding of up to $405 million toward construction, according to Metro Vancouver's project page. The page does not publish a total project budget. The District of North Vancouver's November 10, 2026 budget report to Council names the plant as the main driver of utility rate pressure and notes that longer-term regional costs remain a significant financial risk, but does not publish a total cost figure in that report.

When will the plant be built?

Metro Vancouver's project page sets the primary construction period from 2025 to 2030. The existing Lions Gate plant will be decommissioned after 2030. The project has three parts: the new treatment plant, the First Narrows Pump Station and three kilometres of conveyance pipes (which were completed in September 2022), and design work for decommissioning the Lions Gate facility.

Why are District of North Vancouver utility rates rising 7.4% in 2027?

The District's November 10, 2026 budget report to Council puts the combined utility rate outlook at 7.4%. The report names the North Shore Wastewater Treatment Plant as the main driver of that pressure. Metro Vancouver charges the municipalities it serves for regional infrastructure, and those charges pass through to residents in their utility bills. The report notes that longer-term regional costs and wet-weather pricing remain significant financial risks beyond 2027.

When does District of North Vancouver Council vote on utility rates?

According to the November 10, 2026 budget report to Council, updated utility rate recommendations, including their household impacts, will go to Council on December 7, 2026. That recommendation is separate from the property tax budget, which Council is voting on November 23, 2026.

What did councillors promise about the wastewater plant's cost?

Several members of the new Council made campaign commitments about the plant. Councillor Lisa Muri committed to containing spending and reducing the property tax increase to help offset the utility bill. Councillor Jim Hanson pledged to speak out for a public inquiry into the plant. Councillor Jordan Back promised to push for transparency and accountability at Metro Vancouver, including a public inquiry, and to seek help from other levels of government to ease the cost for residents. Councillor Daniel Anderson committed to fighting for a fair split of the plant's levies to ease the impact on North Vancouver households. Councillor Catherine Pope wrote that she has demanded answers on the plant since 2024 and will keep fighting for lower utility bills. All of these commitments are listed as not started on the promise tracker.

What is the Acciona settlement and what does it mean for utility rates?

The District's November 10, 2026 budget report to Council refers to the Acciona settlement and says Metro Vancouver is updating its financial forecasts to reflect its impact. The report says there may be some near-term reduction in utility rate pressure as a result, though longer-term regional costs remain a significant risk. The report does not specify a dollar amount for the settlement in this document.

Where can I follow the December 7 utility rate decision?

Council agendas and reports for the December 7, 2026 meeting will be posted on the District's document site at dnv.org when they are published, typically the week before the meeting. You can also follow the councillors' promise tracker at the link at the end of this article, which tracks their commitments on utility bills and Metro Vancouver.

Sources

The pages this story draws on. Open one to check a claim yourself.

  1. Metro Vancouver: North Shore Wastewater Treatment Plant project pagemetrovancouver.org
  2. District of North Vancouver: 2027 Budget and Financial Plan, Report to Council, November 10, 2026 (item 3.1, Council meeting November 23, 2026)docs.dnv.org
  3. District of North Vancouver: Council document sitemap (agendas and minutes)dnv.org
  4. The North Shore Local: North Shore Wastewater Treatment Plant construction to begin in 'earnest': Metro Vancouver, April 2, 2024thenorthshorelocal.com

Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.