Fraser Highway in Surrey goes eastbound-only from November 27 to 30 for SkyTrain gantry work
Fraser Highway between 152 Street and 88 Avenue in Surrey will carry eastbound traffic only from 10 p.m. Friday November 27 to 5 a.m. Monday November 30. The restriction is for disassembly of the Fleetwood Flyer launching gantry used in SkyTrain construction. TransLink routes 320 and 502 will detour.
Reported. A news outlet found this. voche.me names the outlet and links its report. Read the original report on surreylangleyskytrain.gov.bc.ca.

Fraser Highway between 152 Street and 88 Avenue in Surrey will carry eastbound traffic only from 10 p.m. on Friday November 27 to 5 a.m. on Monday November 30. Work crews are disassembling the Fleetwood Flyer launching gantry, the large steel structure used to build the Surrey Langley SkyTrain elevated guideway east of 152 Street.
The Surrey Langley SkyTrain project published the traffic notice. Extended construction hours begin at 6 p.m. on Thursday November 26 and run until 6 a.m. Monday November 30. The 60-hour window covers the full weekend to allow crews to complete the gantry disassembly without interruption.
The Fleetwood Flyer was used to lift and place the precast concrete segments that form the guideway for the Surrey Langley SkyTrain extension. Now that the guideway is complete in that section, the gantry is no longer needed and is being taken apart.
Westbound detour
Westbound through traffic must use the signed alternate route via 88 Avenue and 152 Street. Local westbound access remains available between 88 Avenue and Fleetwood Way. Signed detour routes are in place for the duration of the restriction.
Transit changes
TransLink routes 320 and 502 will detour starting at 8 p.m. on Friday November 27, two hours before the road restriction takes effect. The detour runs until 5 a.m. on Monday November 30. Riders should check TransLink service alerts for their specific stop before travelling, as boarding points may shift during the detour period.
What drivers and riders should do
Check the Surrey Langley SkyTrain project site at surreylangleyskytrain.gov.bc.ca before Friday evening. Plan for the westbound detour via 88 Avenue and 152 Street from 10 p.m. Friday to 5 a.m. Monday. If taking the bus, check the TransLink alert for your specific stop, as the detour changes where buses stop along the affected routes. The project's 24/7 construction line is 1-844-815-6111.
Surrey transit and road updates are covered at /bc/surrey-2026/news.
Questions this story answers
When is Fraser Highway restricted in Surrey in late November 2026?
Fraser Highway between 152 Street and 88 Avenue in Surrey will carry eastbound traffic only from 10 p.m. on Friday November 27 to 5 a.m. on Monday November 30, 2026. The restriction is to allow crews to disassemble the Fleetwood Flyer launching gantry used to build the Surrey Langley SkyTrain elevated guideway.
What is the alternate route for westbound traffic on Fraser Highway?
Westbound through traffic must use the signed alternate via 88 Avenue and 152 Street. Local westbound access remains available between 88 Avenue and Fleetwood Way, according to the Surrey Langley SkyTrain project notice.
What TransLink bus routes are affected?
TransLink routes 320 and 502 will detour starting at 8 p.m. on Friday November 27 until 5 a.m. on Monday November 30. Riders should check TransLink service alerts for their specific stop before travelling.
Why is Fraser Highway being restricted?
Work crews are disassembling the Fleetwood Flyer launching gantry, the large steel structure used to build the Surrey Langley SkyTrain elevated guideway east of 152 Street. The Surrey Langley SkyTrain project says extended construction hours run from 6 p.m. Thursday November 26 to 6 a.m. Monday November 30.
Who can residents contact about the Fraser Highway construction?
The Surrey Langley SkyTrain project can be reached by phone at the 24/7 construction line 1-844-815-6111 or through the contact form on its website at surreylangleyskytrain.gov.bc.ca. Both are available around the clock during active construction periods.
Is this the same restriction that ran earlier in November?
No. An earlier restriction between 140 Street and 96 Avenue is a separate, ongoing weeknight closure. The November 27 to 30 restriction is a separate event at a different stretch of Fraser Highway, between 152 Street and 88 Avenue.
Where can Surrey residents find the latest SkyTrain construction traffic updates?
The Surrey Langley SkyTrain project publishes traffic updates at surreylangleyskytrain.gov.bc.ca, including notices for all upcoming road restrictions tied to construction. Surrey council's decisions about roads and transit are covered at /bc/surrey-2026/news.
What is the Fleetwood Flyer gantry?
The Fleetwood Flyer was the large launching gantry used to lift and place segments of the Surrey Langley SkyTrain elevated guideway. Now that the guideway is built in that area, crews are disassembling the gantry, which requires the eastbound-only restriction on Fraser Highway.
Sources
The pages this story draws on. Open one to check a claim yourself.
- Surrey Langley SkyTrain project: Eastbound traffic only on Fraser Highway between 152 Street and 88 Avenuesurreylangleyskytrain.gov.bc.ca
- deeparrival.com: Surrey Cuts Westbound Access on Fraser Highway Nov. 27 to 30deeparrival.com
Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.