Review of Massey Tunnel replacement paused as new BC government weighs bridge option
The provincial environmental review of the Massey Tunnel replacement has been paused at the new government's request, putting the $8.5 billion project on hold for Richmond commuters.
Long read. The subject the most local outlets covered that day, with the public record behind it. Every outlet and record is linked under the story. Read the original report on pqbnews.com.

The province paused the environmental review of the George Massey Tunnel replacement on November 17, 2026, putting the $8.5 billion project on hold as the incoming BC Conservative government decides whether to build a bridge instead. For Richmond, which sits at the north end of the 65-year-old crossing, the pause means more time living with the existing tunnel before any new structure carries Highway 99 traffic under the South Arm of the Fraser River.
What was paused and when
The BC Environmental Assessment Office was in the final stage of its review of the tunnel replacement when the Transportation Investment Corporation asked it to stop. Olivia Stanley, the corporation's executive director of regulatory affairs, submitted the pause request on November 16, citing a need to let the incoming government set its direction. Breanna Merrigan, the EAO's project assessment director, approved the pause the next day, November 17, and asked the corporation to stay ready to restart without delays.
The EAO review had reached what the agency calls the effects assessment and recommendations phase, the last step before a decision on whether to approve the project. The pause stops that work from concluding while the new government conducts its own review.
The tunnel project and what it would do for Richmond
The Transportation Investment Corporation, which manages the project, says the new tunnel would replace the existing crossing with an eight-lane immersed tube tunnel, toll-free, with dedicated bus rapid transit lanes and paths for pedestrians and cyclists. The corridor runs between Bridgeport Road in Richmond and Ladner Trunk Road in Delta. The corporation's project page states a completion date of 2031 and a cost of $8.5 billion.
The existing George Massey Tunnel is 65 years old. It carries Highway 99 south from Richmond to Delta and on toward the US border. The Transportation Investment Corporation's project page says the new tunnel will add dedicated bus rapid transit lanes and paths for pedestrians and cyclists, features the current tunnel does not have.
What the new government wants instead
Premier-designate Lorne Doerkson takes office November 20, 2026. He stated in a November 12 press release that the province should not spend more money or make new commitments that lock British Columbians into the tunnel option before his government completes its review.
Doerkson has proposed a 10-lane bridge as an alternative. He says the bridge would cost $6 billion, compared with the tunnel's $8.5 billion, and would take five years to build. He says the $2.5 billion difference could go toward a women and children's hospital in Surrey.
The original bridge plan, proposed by the BC Liberal government in 2017, had a cost estimate of $3.5 billion, or $4.5 billion in adjusted dollars, according to Parksville Qualicum News. Doerkson's new bridge estimate of $6 billion is higher than that adjusted figure.
Workers affected
CTV News reported on November 20, 2026 that dozens of workers have been laid off amid the uncertainty over the project. The article did not name the contractor or the union involved. Work on the tunnel was well into the construction planning phase before the pause was called.
Outgoing NDP Transportation Minister Mike Farnworth said in a statement that cancelling the project would cost British Columbians hundreds of millions of dollars, lay off hundreds of workers, and leave people stuck in traffic for years longer. He said Premier-designate Doerkson already knows this. Farnworth's statement describes the full cancellation scenario; the current pause is a hold on the environmental review, not a cancellation order.
What comes next
No date has been set for when the review might resume. The EAO asked the Transportation Investment Corporation to maintain readiness to restart without delays. The timeline now depends on the direction the new Conservative government gives after completing its review. Doerkson takes office November 20, the same day this article publishes, so his government's review could begin immediately.
A switch from tunnel to bridge would require a new environmental assessment process, since the EAO was reviewing the tunnel design and not any bridge proposal. Starting over on the assessment could add years to the timeline before any new crossing opens. The existing tunnel would continue to carry traffic in the meantime.
For Richmond residents, the existing 65-year-old tunnel remains the crossing while the province works through its decision. Councillor Sheldon Starrett listed transit solutions as one of his priorities when he was elected in October 2026. His commitments and those of Mayor Rob Howard and the rest of the new Richmond Council can be followed at /bc/richmond-2026/tracker.
What residents can do
The incoming government has not opened a public comment period on the bridge-versus-tunnel decision. Residents who want to follow the review can track the Transportation Investment Corporation's announcements at ticorp.ca and the EAO's project page at eao.gov.bc.ca. If and when the province opens a process for public input on the bridge option, it would be posted on those pages.
Questions this story answers
What happened to the George Massey Tunnel replacement project?
On November 17, 2026, the BC Environmental Assessment Office approved a pause in its review of the tunnel replacement project. The Transportation Investment Corporation requested the pause on November 16 to allow the incoming BC Conservative government to decide whether to continue with the tunnel or build a bridge instead. The project had been in the final phase of its environmental review.
Who requested the pause in the environmental assessment?
Olivia Stanley, the Transportation Investment Corporation's executive director of regulatory affairs, submitted the pause request on November 16, 2026. She said the purpose was to allow the incoming government to establish its priorities for the crossing. Breanna Merrigan, the EAO's project assessment director, approved the request the following day.
What is the new BC government proposing instead of the tunnel?
Premier-designate Lorne Doerkson, who takes office November 20, 2026, has proposed building a 10-lane bridge instead of the eight-lane tunnel. He says the bridge would cost $6 billion and take five years to complete, compared with the tunnel's $8.5 billion cost and 2031 completion date. The $2.5 billion difference, he says, would go toward a Surrey women and children's hospital.
How does the Massey Tunnel replacement affect Richmond?
The George Massey Tunnel carries Highway 99 under the South Arm of the Fraser River between Bridgeport Road in Richmond and Ladner Trunk Road in Delta. The existing tunnel is 65 years old. Whether the province builds a tunnel or a bridge, Richmond sits at the north end of the crossing and would be directly affected by construction and by the final design.
Have workers been laid off because of the pause?
CTV News reported on November 20, 2026 that dozens of workers have been laid off amid uncertainty over the project. Outgoing NDP Transportation Minister Mike Farnworth warned that cancelling the project would lay off hundreds of workers. The article did not name the contractor or the union involved.
What did the outgoing NDP government say about the pause?
Outgoing Transportation Minister Mike Farnworth said in a statement that cancelling the project would cost British Columbians hundreds of millions of dollars, lay off hundreds of workers, and leave people stuck in traffic for years longer. He said Premier-designate Doerkson already knows this.
What was the original cost of the bridge proposal?
The original bridge plan, proposed by the BC Liberal government in 2017, carried a cost estimate of $3.5 billion, which Parksville Qualicum News reported would be $4.5 billion in adjusted dollars. The incoming Conservative government's bridge cost estimate is $6 billion, according to Premier-designate Doerkson's own statements.
When will the environmental assessment resume?
No date has been set for the review to resume. EAO project assessment director Breanna Merrigan asked the Transportation Investment Corporation to stay ready to restart without delays. The assessment will resume once the incoming government completes its review and gives direction on whether to proceed with the tunnel or switch to a bridge.
Where can Richmond residents follow the promise tracker for the people they elected?
Richmond's elected council and school board are tracked at /bc/richmond-2026/tracker, where each person's commitments and their status are recorded. Transportation promises by councillors such as Sheldon Starrett, who listed transit solutions among his priorities, can be found on their individual pages.
Sources
The pages this story draws on. Open one to check a claim yourself.
- Parksville Qualicum News: Environmental assessment of Massey Tunnel replacement paused (November 19, 2026)pqbnews.com
- CTV News Vancouver: B.C. Environmental Assessment Office pauses review of Massey Tunnel project (November 19, 2026)ctvnews.ca
- CTV News Vancouver: Dozens laid off amid uncertainty over Massey Tunnel replacement (November 20, 2026)ctvnews.ca
- Transportation Investment Corporation: Highway 99 Tunnel Programticorp.ca
Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.