Pipeline Road water main work delayed by one year, now expected to finish in early 2028
Metro Vancouver announced November 24 that Phase 1 of the Coquitlam Water Main project, running along Pipeline Road from Robson Drive to Guildford Way, will finish about a year later than planned after Telus cable conflicts halted work for ten months.