Pipeline Road water main work delayed by one year, now expected to finish in early 2028
Metro Vancouver announced November 24 that Phase 1 of the Coquitlam Water Main project, running along Pipeline Road from Robson Drive to Guildford Way, will finish about a year later than planned after Telus cable conflicts halted work for ten months.
Reported. A news outlet found this. voche.me names the outlet and links its report. Read the original report on freshetnews.ca.

Drivers who use Pipeline Road in Coquitlam should plan for continued construction through early 2028, about a year later than originally scheduled, after underground utility conflicts delayed Metro Vancouver's water main project by ten months.
Metro Vancouver announced the revised timeline on November 24, Freshet News reported. Mayor Craig Hodge and council were briefed at the November 23 committee meeting, where the city received a second trimester progress report on the project.
What caused the delay
When the contractor opened Pipeline Road for the new water main, Telus cables were found in a different location than what Metro Vancouver's records showed. The regional agency had to request a redesign from Telus and relocate the cables before work could continue. BC Hydro's underground work in the area was then halted while the cable conflict was being resolved.
Metro Vancouver senior engineer Arezoo Heidarian told Freshet News: "There was a cascading of delays. It took 10 months to resolve the conflict, but it was out of our control."
Telus and BC Hydro have since completed their work along Pipeline Road. As of the announcement, 1,200 of the 1,400 metres of Phase 1 have been installed, Heidarian said.
The project
The Coquitlam Water Main is a 12-kilometre line running from the northern end of Pipeline Road to Mariner Way at Riverview Crescent. Metro Vancouver has divided the work into four sections: Robson to Guildford, Cape Horn, Pipeline Road North, and a City Centre tunnel. Phase 1, the Robson to Guildford section, spans 1.4 kilometres and the pipe measures 3.2 metres in diameter. Construction on that section started in fall 2023.
The full project runs from 2023 to 2034, according to Metro Vancouver's project page.
What the city is doing
Jaime Boan, Coquitlam's general manager of engineering and public works, told the committee that city staff maintain weekly contact with Metro Vancouver and are working to keep traffic disruptions and noise as low as possible, Freshet News reported.
Hodge suggested adding more road signage along Pipeline Road to inform commuters about the extended timeline. "The city and Metro Vancouver are taking the heat for third-party issues," Hodge said.
Heidarian declined to disclose the financial impact of the delay. Metro Vancouver said it will update nearby residents through newsletters and meetings, with a community liaison officer collecting feedback. Residents can contact Metro Vancouver by phone at 604-432-6200.
Drivers can check the City of Coquitlam's website at coquitlam.ca or follow the city on social media for traffic updates on Pipeline Road.
Questions this story answers
How long is Phase 1 of the Coquitlam Water Main project delayed?
Phase 1, which runs along Pipeline Road from Robson Drive to Guildford Way, is now expected to finish in early 2028. Metro Vancouver announced the delay on November 24, 2026. The original schedule was not given in the announcement, but the new completion date is about one year later than previously planned, Freshet News reported.
What caused the delay on Pipeline Road?
When the contractor opened Pipeline Road for the new water main, Telus cables were found in a different location than the documented records showed. Metro Vancouver had to request a redesign from Telus and move the cables. BC Hydro's underground work in the area was then halted while the conflict was resolved. Metro Vancouver senior engineer Arezoo Heidarian said: 'There was a cascading of delays. It took 10 months to resolve the conflict, but it was out of our control.'
How much of Phase 1 has been installed as of November 2026?
Metro Vancouver senior engineer Arezoo Heidarian told Freshet News that 1,200 of the 1,400 metres of Phase 1 have now been installed. Telus and BC Hydro have both completed their work along Pipeline Road, Freshet News reported on November 25.
What is the full scope of the Coquitlam Water Main project?
The project is a 12-kilometre water main running from the northern end of Pipeline Road to Mariner Way at Riverview Crescent. It is divided into four sections: Robson to Guildford, Cape Horn, Pipeline Road North, and a City Centre tunnel. Metro Vancouver says the full project runs from 2023 to 2034. Phase 1, the Robson to Guildford section, spans 1.4 kilometres and the pipe measures 3.2 metres in diameter. Construction on that section started in fall 2023.
What is Coquitlam doing about traffic during the delay?
Mayor Craig Hodge suggested adding more road signage to alert commuters and residents about the extended timeline at the November 23 Coquitlam council committee meeting. Hodge said: 'The city and Metro Vancouver are taking the heat for third-party issues.' The City's general manager of engineering and public works, Jaime Boan, said city staff maintain weekly contact with Metro Vancouver and are working to keep traffic impacts as small as possible, Freshet News reported.
What financial impact has the delay had?
Metro Vancouver senior engineer Arezoo Heidarian declined to disclose the financial impact of the delays, telling Freshet News: 'For now, our focus is to finish the work.' No cost figure for the delay was published.
How will Metro Vancouver keep residents informed about the project?
Metro Vancouver told Freshet News it will update nearby property owners through newsletters and meetings. A dedicated community liaison officer is collecting feedback. Residents can also contact Metro Vancouver by phone at 604-432-6200 or through the contact form on metrovancouver.org.
Where can Coquitlam residents find more information about the water main project?
Metro Vancouver's project page at metrovancouver.org describes the full 12-kilometre Coquitlam Water Main project, which runs from 2023 to 2034. For current road conditions on Pipeline Road, residents can check the City of Coquitlam's website at coquitlam.ca or follow the city on social media for traffic updates.
Sources
The pages this story draws on. Open one to check a claim yourself.
- Coquitlam water main install delayed by a year - Freshet Newsfreshetnews.ca
- Coquitlam water utility projects - Metro Vancouvermetrovancouver.org
Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.