Six problems found during O-Train east extension testing, work to restart December 5
A memo from OC Transpo's general manager lists six technical issues found during preliminary testing of the O-Train east extension that need to be fixed before the next phase can begin.
Reported. A news outlet found this. voche.me names the outlet and links its report. Read the original report on ottawa.citynews.ca.

After a week of full-line testing on the O-Train east extension, OC Transpo has found six technical problems that need to be fixed before the next phase of testing can begin. CityNews Ottawa reported the findings on Friday, citing a memo from Rick Leary, general manager of transit services.
What the testing found
The preliminary testing ran the full line from Tunney's Pasture to Trim stations, with 23 trains operating at 4.5-minute intervals during peak periods. Passengers still had to change at Blair Station, as the east extension has not opened to the public.
The six issues Leary's memo lists:
- The power supply system between Blair and Trim stations needs improvement
- Trains are not consistently departing from the rail yard at the start of service
- Vehicles are not consistently available for service
- The train control system performance in the east extension needs improvement
- A switch near Blair Station needs repair
- Software issues are affecting vehicles docking at Trim Station
Rideau Transit Maintenance and East-West Connectors, the contractors responsible for the system, are responsible for addressing each item.
What happens next
Testing will continue through the evening of November 27, then stop while repair work takes place. CityNews Ottawa reports there will be no testing on the east end of the line until December 5.
"We are assessing operations and need to see progress on the items above to determine readiness to advance to the next phase of testing," Leary said in the memo.
OC Transpo says the fixes are expected to give the system more room to handle disruptions and return to normal operations faster after a problem occurs.
The bigger picture
The east extension runs from Blair Station to Trim Station, adding stops at Montreal Road, Jeanne d'Arc, Orléans, Convent Glen, Place d'Orléans and Trim. Full-line testing started on November 22.
Separately, the City of Ottawa and the Ontario government signed an agreement in April to advance a potential provincial takeover of Line 1. Mayor Mark Sutcliffe said at the time there is no timeline yet and called the agreement a framework for how the work gets done. The province reconfirmed its commitment during the same period.
Residents following the east extension can track updates on the voche.me Ottawa news page.
Questions this story answers
What six issues were found during O-Train east extension testing?
According to a memo from OC Transpo general manager Rick Leary, the six issues are: improvements needed to the power supply system between Blair and Trim stations; trains not consistently departing from the rail yard at the start of service; vehicles not consistently available for service; improvements needed to the train control system performance in the east extension; a switch near Blair Station that needs repair; and software issues affecting vehicles docking at Trim Station.
When will O-Train east extension testing resume after the pause?
CityNews Ottawa reports that OC Transpo will continue testing until the evening of November 27, 2026. After that, crews will make repairs and there will be no testing on the east end of the line until December 5, 2026.
What phase of testing was the O-Train east extension in when these issues were found?
The issues were found during preliminary testing that OC Transpo started after putting the whole line into use from Tunney's Pasture to Trim stations. CityNews Ottawa reports 23 trains were running, each at the 4.5-minute mark during peak periods, but passengers still had to get off at Blair Station.
What did OC Transpo's general manager say about the issues found?
In his memo, Rick Leary said: 'Identifying these issues is a normal part of the testing process and a fundamental objective of the current phase of testing. It is important that we identify issues at this stage to provide sufficient opportunity to make necessary corrections and improvements.' He also said the city is assessing operations and needs to see progress on the listed items to determine readiness to advance to the next phase of testing.
Who is responsible for fixing the issues found in the east extension testing?
According to the memo reported by CityNews Ottawa, the items need to be addressed by Rideau Transit Maintenance and East-West Connectors. These are the two contractors responsible for maintaining and operating the O-Train system under their agreements with the City of Ottawa.
What is the status of the province potentially taking over Ottawa's LRT system?
CityNews Ottawa reports that Mayor Mark Sutcliffe said in April that there is no timeline yet, but the City of Ottawa and the Ontario government signed an agreement to advance the upload of Line 1 to the province. Sutcliffe called it a 'milestone' and said the agreement outlines collaboration between the two levels of government.
What improvements does OC Transpo expect from fixing these issues?
CityNews Ottawa reports that OC Transpo hopes the upgrades will give the transit system more flexibility when dealing with service disruptions and will shorten the time it takes to return to normal operations after a problem occurs on the line.
Where can Ottawa residents follow O-Train east extension updates?
Residents can follow the O-Train east extension story and other Ottawa transit news on voche.me's Ottawa news page at /on/ottawa-2026/news. OC Transpo also posts service updates on its own website and social media channels when testing milestones are reached.