Construction on Kelowna's $18 million City Park swim venue starts Monday
Work begins November 23 on the new Okanagan Lake swim venue, closing a section of the City Park waterfront promenade until spring 2027. The venue will offer eight 50-metre swim lanes and free public access when it opens in fall 2027.
Long read. The subject the most local outlets covered that day, with the public record behind it. Every outlet and record is linked under the story. Read the original report on kelowna.ca.

Work on Kelowna's new Okanagan Lake swim venue starts Monday, November 23, closing a section of the City Park waterfront promenade until spring 2027. The City of Kelowna announced the construction timeline in a news release on November 20.
The $18 million project, built in partnership with the Swim Drink Fish Foundation, is set to open in fall 2027. It will give Kelowna residents free public access to Okanagan Lake from a purpose-built waterfront structure in City Park.
What is being built
The Swim Drink Fish Foundation says the venue will include eight 50-metre swim lanes, a multi-height jumping platform, space for water polo, a seasonal accessible gangway, a nordic cold-plunge area, sun decks and shade areas, outdoor showers, accessible changerooms and gathering spaces.
The foundation says public access to the finished venue will be free, and the design includes accessible changerooms and outdoor showers so the facility works for people who arrive on foot, by bike or by transit.
The City of Kelowna says the venue will improve safe access to the waterfront, support active lifestyles and provide a new gathering place that connects residents and visitors to the lake.
How the construction works
The initial phase of work focuses on the on-land parts of the project: the supporting amenities, washroom facilities and shoreline improvements along the City Park waterfront. The swim structure itself will be built off-site and floated into its permanent waterfront location at a later stage of the project, Castanet reported on November 20.
That two-stage approach means the most visible part of the venue, the in-water structure, will not be in place until after the on-land work is done. The City says the full project is on track for a fall 2027 completion.
What closes and for how long
The closure will affect the section of the Waterfront Promenade near the Cold Sands washroom. The City says that portion will stay closed until spring 2027. As work moves into later phases, the City expects additional temporary closures along the promenade.
Signed pedestrian detours will be in place throughout the construction period to keep the surrounding waterfront accessible. The City is asking residents and visitors to follow all posted construction signage, fencing and barriers while work continues.
The Cold Sands washroom area is on the south end of the main City Park beach. People walking or cycling the full length of the waterfront trail will need to follow the signed detour around the construction zone.
Where the money comes from
The Swim Drink Fish Foundation says the project received a $12.9 million donation from the Weston family, one of Canada's prominent philanthropic families. The City of Kelowna contributed $5.1 million in capital funding. Together those two amounts total the $18 million project cost Castanet reported.
The foundation says the Kelowna venue was funded through its WAVE Prize, which stands for Waterfront Access, Vitality, and Engagement. Swim Drink Fish uses the prize to support communities that want to restore and expand public access to their waterfronts.
The partnership between the City and Swim Drink Fish means the venue is a jointly planned project, with the foundation leading the design and construction alongside City staff.
Why Kelowna is building this
Swim Drink Fish notes on its project page that Kelowna's growing population has increased demand for waterfront recreation, and that the existing City Park beach does not have a structure designed for lap swimming, water polo or competitive training. The new venue is intended to serve both recreational swimmers and organized aquatic programs throughout the spring, summer and fall seasons.
The foundation also highlights the nordic cold-plunge area as part of a wider range of water uses, from family swimming to year-round cold-water dipping. Sun decks and shade structures will be part of the on-land amenities, so the venue can function as a waterfront gathering place even for people who do not swim.
The foundation describes its goal as reconnecting residents with the lake and supporting community wellbeing alongside year-round waterfront activity.
The City's statement says the investment is intended to create a gathering place for residents and visitors for generations to come, and that the project will improve safe access to the waterfront.
What comes next for residents
Anyone who regularly walks, runs or cycles the City Park waterfront promenade should plan for the closure from Monday, November 23 onward. The signed detour will be in place on site, and the City is asking people to follow all posted signage and fencing around the construction zone.
The in-water swim structure will not be installed until a later stage of the project, well after the on-land work is done. The full venue is expected to open to the public in fall 2027. The City's news release and further project updates are posted at kelowna.ca/newsroom, where the City also publishes its road closure and construction notices.
Questions this story answers
When does construction on Kelowna's City Park swim venue start?
Construction starts on Monday, November 23, 2026, according to the City of Kelowna. The initial phase focuses on on-land components, including supporting amenities and shoreline improvements. The in-water structure will be built off-site and floated into its final waterfront position at a later stage of the project.
How much does the Kelowna City Park swim venue cost?
The project costs $18 million in total. The Swim Drink Fish Foundation says it received a $12.9 million donation from the Weston family and that the City of Kelowna contributed $5.1 million in capital funding. The combined amount is $18 million.
What will the City Park swim venue include?
According to the Swim Drink Fish Foundation, the venue will offer eight 50-metre swim lanes, a multi-height jumping platform, space for water polo, a seasonal accessible gangway, a nordic cold-plunge area, sun decks and shade areas, accessible changerooms and outdoor showers, and gathering spaces. The foundation says public access will be free.
Which part of City Park will close for construction?
The City of Kelowna says a section of the Waterfront Promenade near the Cold Sands washroom will be closed starting November 23. Signed pedestrian detours will be in place to maintain access through the area. Additional temporary closures are expected as construction continues.
When will the City Park closure end and when will the swim venue open?
The City of Kelowna says the promenade closure near the Cold Sands washroom will last until spring 2027. The full project, including the in-water swim structure, is expected to be completed by fall 2027, Castanet reported.
Who is funding the Kelowna swim venue?
The Swim Drink Fish Foundation says the project received a $12.9 million donation from the Weston family. The City of Kelowna is contributing $5.1 million. The foundation is developing the venue in partnership with the City.
What is the Swim Drink Fish Foundation?
Swim Drink Fish is a charitable organization that works to restore and protect public access to waterways. Its site says the Kelowna project was funded through its WAVE Prize, which stands for Waterfront Access, Vitality, and Engagement. The organization leads the design and construction in partnership with the City of Kelowna.
Will the swim venue be free to use?
The Swim Drink Fish Foundation says public access to the swim venue will be free. The City of Kelowna describes the project as a significant investment in recreation and waterfront access. Swim Drink Fish notes that the design includes accessible changerooms and outdoor showers so that the facility works for people who arrive on foot, by bike or by transit, without a car at the waterfront.
Sources
The pages this story draws on. Open one to check a claim yourself.
- City of Kelowna · Partial closure of City Park: Swim venue construction to begin, November 20, 2026kelowna.ca
- Castanet Kelowna · Construction to start on new Okanagan Lake swim venue, November 20, 2026castanet.net
- Beach Radio Kelowna · Construction to close part of Kelowna's City Park waterfront promenade, November 20, 2026beachradiokelowna.ca
- Swim Drink Fish Foundation · Kelowna City Park swim venue project pageswimdrinkfish.ca
Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.