Burke Mountain Community Centre: what Coquitlam is building, and when it opens
Construction is underway on Coquitlam's first new recreation centre in decades. The 80,000-square-foot building opens in 2029 and is backed by $67.4 million in federal funding.
Long read. The subject the most local outlets covered that day, with the public record behind it. Every outlet and record is linked under the story. Read the original report on freshetnews.ca.

Construction is underway on the Burke Mountain Community Centre in Coquitlam, an 80,000-square-foot building in the Partington Creek neighbourhood that will open in 2029. It is the City's first major new recreation facility in decades, backed by $67.4 million from the federal government and $10 million from the province.
Mayor Craig Hodge made the project one of his platform commitments. His promise to deliver the facility is tracked at the Coquitlam promise tracker. Construction was already in progress when Hodge and the new council took office in November 2026, with the opening date and the federal funding agreement both confirmed by the previous administration.
What the building will include
The facility covers 80,000 square feet. Its confirmed amenities, as reported by Freshet News and the Tri-Cities Dispatch, are:
- A six-lane lap pool and a separate leisure pool
- A whirlpool, sauna, and steam room
- Two gymnasiums for basketball, volleyball, pickleball, and badminton
- A fitness centre
- Multipurpose meeting rooms
- A branch of the Coquitlam Public Library
- 237 parking spaces, including 128 underground stalls
- Views of Mount Baker and the Fraser River
Freshet News reported in November 2025 that the building will include two amenities new to Coquitlam recreation. The first is a drop slide in the lap pool that does not need a separate landing pool or additional filtration. The second is the building's energy performance: City staff described it as the most energy-efficient recreation centre the City has built, measured by annual energy use per square metre.
An adjacent 3.48-acre Burke Village Park will be built at the same time. The City and EllisDon are working with the kʷikʷəƛ̓əm (Kwikwetlem) First Nation on cultural recognition elements for the facility.
Who is paying
The federal government committed $67,463,368 through the Direct Delivery stream of the Build Communities Strong Fund. The announcement came in September 2026, and the previous council directed staff to sign the federal agreement on September 21, 2026, as reported by Freshet News. MP Ron McKinnon made the announcement at the construction site.
The province committed $10 million, and the City's Housing Accelerator Fund added $4.6 million. The Tri-Cities Dispatch reported the City's earlier cost estimate at $150 million to $152 million. City staff noted that the final cost is difficult to fix because tariffs and trade conditions were still shifting. The gap will be covered by development contributions from new housing projects in the area and debt financing, with repayment tied to future development.
Mayor Stewart, who served before Hodge, described the federal commitment as "the largest investment in Coquitlam infrastructure by another level of government in our community's history," according to the Tri-Cities Dispatch.
Who is building it
EllisDon Construction Ltd., an employee-owned company, is the construction manager and is responsible for all aspects of the build, including hiring subcontractors. The Tri-Cities Dispatch reported the contractor selection in December 2025.
Site preparation work began in February 2026 and included excavation, shoring, soil removal, tree clearing, and erosion control across the 2.5-acre site. The groundbreaking ceremony was held in May 2026.
Why Burke Mountain
The Partington Creek neighbourhood has grown faster than the rest of Coquitlam over the past decade, with towers and townhouses built along the Evergreen Extension's stations from Burquitlam to Lafarge Lake-Douglas. The City identified the area as underserved by existing facilities, which are concentrated near the City Centre and in the Poirier neighbourhood. The closest existing facility with a pool is the City Centre Aquatic Complex, which is on the opposite side of the city from Partington Creek.
Coquitlam's population grew by more than 15,000 residents between 2016 and 2021, according to Statistics Canada. Burke Mountain and the Lincoln Station area absorbed a large share of that growth. Without a local facility, residents from that side of the city travel across town or to neighbouring Port Coquitlam to reach a pool or gym.
Mayor Hodge's platform named the community centre as a parks and recreation priority for his term. His promise is listed alongside others on the tracker, including plans to expand programs for seniors, improve the Coquitlam Crunch trail, and plan recreation amenities at the Fraser Mills waterfront development. The Fraser Mills project, which the Tri-Cities Dispatch reported is set for construction in 2028, will bring a second new recreation facility to that developing area.
What to know about existing facilities
While the Burke Mountain building is under construction, the City's two existing indoor aquatic and recreation centres remain open. The City Centre Aquatic Complex and the Poirier Sport and Leisure Complex at 633 Poirier Street offer swimming lessons, skating lessons, fitness programs, aquafit classes, and arts programs. Winter registration for general programs opens to Coquitlam residents on November 24. Pro-D Day Camp registration opens November 17. Contact the City's Parks, Recreation, Culture and Facilities department at 604-927-4386 for program details.
What comes next
The 2029 opening date means three years of construction remain. The City's budget decisions in 2027 will confirm the funding plan and schedule for the project. Residents can submit feedback on the 2027 budget, which covers parks and recreation alongside other City services, before the survey closes November 22 at LetsTalkCoquitlam.ca/budget.
For questions about the Burke Mountain project, contact the City of Coquitlam at 604-927-3000 or coquitlam.ca.
Questions this story answers
What is the Burke Mountain Community Centre?
The Burke Mountain Community Centre is a new 80,000-square-foot recreation and community facility under construction in the Partington Creek neighbourhood on Coquitlam's northeastern side. It will include a six-lane swimming pool, a separate leisure pool, two gymnasiums, a fitness centre, multipurpose meeting rooms, a Coquitlam Public Library branch, and 237 parking spaces. Construction began in early 2026 and the building is scheduled to open in 2029.
When does the Burke Mountain Community Centre open?
The opening is scheduled for 2029. The original target was 2027, but the timeline was extended. EllisDon Construction Ltd. is the construction manager. Site preparation work began in February 2026 and included excavation, shoring, and soil removal on the 2.5-acre site.
How much does the Burke Mountain Community Centre cost?
The City's earlier estimate was $150 million to $152 million for the full project. The federal government committed $67.4 million through the Build Communities Strong Fund. The provincial government added $10 million. The City's Housing Accelerator Fund contributed $4.6 million. The remainder is funded through development cash contributions and debt financing, which the City plans to repay from future development projects in the area.
Where is the Burke Mountain Community Centre?
The centre is in the Partington Creek neighbourhood on the northeastern side of Coquitlam. The site also includes an adjacent 3.48-acre Burke Village Park, which will serve as green space for the neighbourhood. The area has seen rapid residential growth over the past decade, and the City has identified it as underserved by existing recreation facilities.
Who is building the Burke Mountain Community Centre?
EllisDon Construction Ltd. is the construction manager and is overseeing all aspects of construction, including hiring subcontractors and managing the schedule. EllisDon is an employee-owned company. The City of Coquitlam and EllisDon are also working with the kʷikʷəƛ̓əm (Kwikwetlem) First Nation on cultural recognition elements for the facility.
What are the two firsts at the Burke Mountain Community Centre?
According to Freshet News reporting from November 2025, the facility will include two amenities new to Coquitlam recreation. The first is a drop slide in the lap pool, which does not require a separate landing pool or additional filtration and pump system. The second is that the building is projected to be the most energy-efficient recreation centre in the City, with lower estimated annual energy use per square metre than other City recreation buildings.
What did Mayor Craig Hodge promise about this project?
Craig Hodge, who was elected mayor in October 2026, committed in his platform to deliver the Burke Mountain Community Centre. The promise is tracked on the voche.me promise tracker for Coquitlam. Construction was already underway before the new council took office, and the 2029 opening date was set by the previous council and City staff.
What can Coquitlam residents do now?
Residents can follow construction updates through the City of Coquitlam's website at coquitlam.ca. They can also submit feedback on the City's 2027 budget, which will shape funding for parks, recreation, and other City services, before the survey closes November 22 at LetsTalkCoquitlam.ca/budget. The City's existing recreation facilities, including the City Centre Aquatic Complex and the Poirier Sport and Leisure Complex, are open now. Winter program registration opens for residents starting November 17.
Sources
The pages this story draws on. Open one to check a claim yourself.
- Freshet News: Coquitlam starts Burke hub build, September 21 2026freshetnews.ca
- Freshet News: Two firsts for Coquitlam recreation in new Burke hub, November 2025freshetnews.ca
- Tri-Cities Dispatch: Feds chip in as much as $67 million on Burke Mountain rec centre, September 9 2026tricitiesdispatch.com
- Tri-Cities Dispatch: Coquitlam picks contractor for Burke Mountain Community Centre, December 2025tricitiesdispatch.com
- City of Coquitlam civic alertscoquitlam.ca
Found an error? Tell the editors with the corrections form. A correction is noted on the story it changes. Read our standards.
Topics
More from voche.me


Water main work starts this month on Pipeline Road in Coquitlam, running 16 months