title: "Six problems found during O-Train east extension testing, work to restart December 5"
description: "A memo from OC Transpo's general manager lists six technical issues found during preliminary testing of the O-Train east extension that need to be fixed before the next phase can begin."
canonical_url: "https://voche.me/on/ottawa-2026/news/o-train-east-extension-testing-issues-december-2026"
last_updated: "2026-11-27T20:46:40.624Z"
---

After a week of full-line testing on the O-Train east extension, OC Transpo has found six technical problems that need to be fixed before the next phase of testing can begin. CityNews Ottawa reported the findings on Friday, citing a memo from Rick Leary, general manager of transit services.

## What the testing found

The preliminary testing ran the full line from Tunney's Pasture to Trim stations, with 23 trains operating at 4.5-minute intervals during peak periods. Passengers still had to change at Blair Station, as the east extension has not opened to the public.

The six issues Leary's memo lists:

- The power supply system between Blair and Trim stations needs improvement
- Trains are not consistently departing from the rail yard at the start of service
- Vehicles are not consistently available for service
- The train control system performance in the east extension needs improvement
- A switch near Blair Station needs repair
- Software issues are affecting vehicles docking at Trim Station

Rideau Transit Maintenance and East-West Connectors, the contractors responsible for the system, are responsible for addressing each item.

## What happens next

Testing will continue through the evening of November 27, then stop while repair work takes place. CityNews Ottawa reports there will be no testing on the east end of the line until December 5.

"We are assessing operations and need to see progress on the items above to determine readiness to advance to the next phase of testing," Leary said in the memo.

OC Transpo says the fixes are expected to give the system more room to handle disruptions and return to normal operations faster after a problem occurs.

## The bigger picture

The east extension runs from Blair Station to Trim Station, adding stops at Montreal Road, Jeanne d'Arc, Orléans, Convent Glen, Place d'Orléans and Trim. Full-line testing started on November 22.

Separately, the City of Ottawa and the Ontario government signed an agreement in April to advance a potential provincial takeover of Line 1. Mayor Mark Sutcliffe said at the time there is no timeline yet and called the agreement a framework for how the work gets done. The province reconfirmed its commitment during the same period.

Residents following the east extension can track updates on the voche.me Ottawa news page.