---
title: "O-Train Line 1 begins full-line testing to Trim Station, but riders still stop at Blair"
description: "Starting November 22, all 23 O-Train Line 1 trains run the whole route from Tunney's Pasture to Trim Station, but riders must still exit at Blair. A one-week gap in extension testing begins November 29."
canonical_url: "https://voche.me/on/ottawa-2026/news/o-train-east-extension-full-line-testing-november-2026"
last_updated: "2026-11-21T23:46:14.838Z"
---

Ottawa's O-Train Line 1 begins its most visible step toward east-end service on November 22: for the first time, trains will run over the whole route from Tunney's Pasture in the west to Trim Station in the east. No riders will board past Blair Station yet, but the testing marks a turning point after years of delay on the city's most-watched transit project.

The City of Ottawa announced the testing phase on November 20. OC Transpo has not given a date for when the five new stations will open to passengers.

## What testing means for riders now

The City's announcement carries a warning that matters to anyone catching a train east of downtown. Starting November 22, every train's destination sign and next-departure display will read Trim Station. That is the testing system running as it will run when the extension opens. But riders cannot board past Blair Station. OC Transpo staff will be at Blair to direct passengers who may try to continue east.

This is not the first adjustment riders have made for the extension's testing phases. On November 15, Line 1 did not start until noon. The late start was needed for software updates, the City said, to allow testing of vehicles, operational schedules, and staff assignments.

The testing phase is not steady. The week of November 29, trains will not enter the east extension at all. EWC, the contractor, asked OC Transpo to keep trains out of the extension that week so its crews can complete track infrastructure upgrades. Regular Line 1 service from Tunney's Pasture to Blair continues that week without change.

## The five stations waiting to open

The east extension adds five stations along 12.5 kilometres east of Blair. Montreal Station comes first, then Jeanne d'Arc, Convent Glen and Place d'Orléans. Trim Station is the new eastern end of Line 1. The Ottawa Citizen reported in November that 23 trains will run every 4.5 minutes at launch, the same intervals as the main line.

Riders in Orléans and the east end have been waiting longer than the City originally planned. The extension was originally scheduled to open by the end of 2025. OC Transpo has not announced when the five stations will accept passengers.

## The stages still ahead

Full-line testing is one step in a process. The City's release calls it part of a staged approach and an important step toward the final phases before the extension opens. The Ottawa Citizen reported those final phases as pre-trial running, expected to last about one week, followed by 21 days of trial running. Only after those phases does the extension open to riders. The City has not set dates for pre-trial running.

Councillor [Rawlson King](/on/ottawa-2026/candidates/rawlson-king), who represents Rideau-Rockcliffe Ward and was re-elected in October, named LRT extensions to Orléans as one of the things he expects will improve transit access across Ottawa. Speaking to Capital Current on November 19, he said transit reliability was the top concern he heard at the doors during the campaign. He added that he wants the City to adopt binding OC Transpo service standards so riders know what they are entitled to and can hold the service to published benchmarks.

## What Mayor Sutcliffe promised

Mayor [Mark Sutcliffe](/on/ottawa-2026/candidates/mark-sutcliffe) made transit a central part of his re-election platform. He promised to include a $95 monthly transit pass in Budget 2027 and said he would keep securing investment from federal and provincial governments for new rapid transit lines. His transit promises are tracked at [/on/ottawa-2026/tracker](/on/ottawa-2026/tracker), including his commitment to direct staff in his first 30 days to include the $95 pass in the 2027 budget. The east extension's opening will be a test of whether that expansion of service aligns with the lower-cost pass he has staked his transit agenda on.

The east extension is a Stage 2 LRT project approved under a previous council. The City has not announced a capital cost figure for the extension separate from the broader Stage 2 project.

## What residents can do

Riders who use Line 1 east of downtown should check their train's destination sign starting November 22. The sign will show Trim even though the train stops at Blair. OC Transpo staff will be at Blair Station to help. During the week of November 29, trains will not run into the extension: riders needing service east of Blair should watch OC Transpo's announcements for any replacement service or changes.

The City updates its newsroom at ottawa.ca as the testing phases proceed. The next step is pre-trial running, which the Ottawa Citizen reported is expected to last about one week. Then comes 21 days of trial running. OC Transpo will announce when each phase begins and what service changes, if any, come with it. Residents in the east end can track updates at the City's newsroom and through OC Transpo's official channels.

## Sitemap

See the full [sitemap](/on/ottawa-2026/sitemap.md) for all pages.
