title: "Vancouver's new $91-million Marpole Community Centre opens at 7780 Oak Street"
description: "The new Marpole Community Centre opened November 16, 2026, replacing a 1949 building with a 42,000-square-foot mass-timber facility that includes childcare for 74 children."
canonical_url: "https://voche.me/news/marpole-community-centre-opens-november-2026"
last_updated: "2026-11-17T08:15:23.663Z"
---

Vancouver opened its new Marpole Community Centre on November 16, 2026, replacing a 77-year-old building with a $91-million, 42,000-square-foot facility at 7780 Oak Street in Oak Park. Daily Hive Vancouver reported the opening, noting it is the first newly-built community centre the City has opened in about 14 years.

## What is in the building

The two-storey centre holds a gymnasium, fitness centre, fieldhouse, studios and multi-purpose rooms, a sensory room, and a commercial kitchen, according to Daily Hive. Childcare for up to 74 children occupies the second floor, operated by the Vancouver Society of Children's Centres. Underground parking fits about 100 vehicles. Outside, the site has basketball courts and an outdoor performance space.

A second phase will add an outdoor aquatic centre. The 2027 to 2030 capital plan includes funding for design and planning of a 10,500-square-foot outdoor pool complex, with five lap lanes, a leisure pool and a hot whirlpool. Construction funding has not been approved yet.

## How it was funded

The Vancouver Park Board confirmed the $91-million project cost on the day of opening. The federal government contributed $2.16 million through the Build Communities Strong Fund, announced April 7, 2026, and the Province contributed $3 million through the Growing Communities Fund. The City covered the remainder.

## The building's design

Toronto-based Diamond Schmitt Architects designed the centre using a mass-timber structure with glulam columns and beams, cross-laminated timber floors, and a hybrid CLT and steel roof. Daily Hive reported the structure cuts embodied carbon by 41 per cent compared to conventional construction. The project is part of BC's Mass Timber Demonstration Program. The building is targeting Passive House and LEED Gold certifications, as well as Rick Hansen Foundation Accessibility Certification Gold, which would make it the first City-owned community centre to achieve that designation.

General contractor Heatherbrae Builders began construction in November 2023.

## The old building

The original Marpole-Oakridge Community Centre opened in 1949 and was Vancouver's oldest community centre at the time it closed. The community association traces its history to 1940. The old building closed permanently in late October 2026 and will be demolished.

A September 2025 report from the City Auditor General found that 72 per cent of Vancouver's community centres, aquatic centres and ice rinks were rated in poor or worse condition, with an annual infrastructure funding shortfall of $33 million across 46 facilities.

## What residents can do

The fitness centre and fall programs are running now at 7780 Oak Street. Programs run through December 24, 2026. A formal opening celebration is planned for early 2027. Residents can register for programs through the City of Vancouver's parks and recreation registration system.

## Sitemap

See the full [sitemap](/sitemap.md) for all pages.