title: "Broadway Subway construction is closing streets in Vancouver until January 2027"
description: "Broadway between Cambie and Alberta streets is closed to vehicles until January 2027 as crews backfill, install utilities, and rebuild the road above the new station box."
canonical_url: "https://voche.me/news/broadway-subway-construction-disruptions-november-2026"
last_updated: "2026-11-17T08:15:23.795Z"
---

The Broadway Subway Project is in its final construction phase across six underground stations in Vancouver, with several stretches of Broadway and nearby streets closed or reduced to one lane while crews complete backfilling, utility work, and road rebuilding above each station box. The project is scheduled to open in 2027.

The most visible closure runs along West Broadway between Cambie and Alberta streets, where the road is shut to vehicles. The project's current work page says the closure will last until January 2027. Pedestrian access to businesses and residences in the area is maintained throughout. The detour for vehicles and transit buses runs via West 8th Avenue.

## What the project is

The Broadway Subway extends the Millennium Line 5.7 km west from VCC-Clark Station to Broadway and Arbutus. It adds six underground stations: Great Northern Way-Emily Carr, Mount Pleasant, Broadway-City Hall, Oak-VGH, South Granville, and Arbutus. At Cambie Street, the new line connects directly to the Canada Line. The project costs $2.83 billion, according to the Wikipedia article on the extension. Train testing began in May 2026, and by September 2026 all track rails and power rails were installed from one end of the line to the other.

## What is closed right now

The Broadway Subway Project's current work page, updated through November 2026, lists active closures at four stations along the corridor.

At Broadway-City Hall Station, Broadway between Cambie and Alberta streets is closed to vehicles until January 2027, the project page says. Crews have removed all 133 traffic deck panels and their supporting girders to access the station box below and are now backfilling, relocating utilities, and rebuilding the road surface. The closure has been in place since May 2026. West 8th Avenue has served as the alternate route for both vehicles and transit buses during that time.

At Oak-VGH Station, West Broadway between Oak and Laurel streets is reduced to one lane in each direction. A project update posted November 3 says crews began water main tie-in work around November 2 for two weeks, running from 10 pm to 6 am. Work during the day covers station fitting out, backfilling, and road restoration.

At South Granville Station, West Broadway between South Granville and Hemlock is reduced to one lane in each direction. Hemlock Street is closed to southbound traffic between West 8th Avenue and south of West Broadway, where crews are completing permanent utility work.

At Arbutus Station, West Broadway between Arbutus and Cypress streets is reduced to one lane in each direction. Arbutus Street is one-way southbound only between Broadway and West 8th Avenue. Maple Street near Broadway is closed to vehicles. A project update from October 23 says traffic on West Broadway between Arbutus and Cypress shifted to the north side of the road on November 2, with overnight lane repainting completing the change.

## Testing and station finishing

At Great Northern Way-Emily Carr Station, a November 6 project update says dynamic testing is underway on the elevated guideway. Dynamic testing means test vehicles run along the track to check the rail, signals, and systems before the line opens. Interior work at the station includes wall tiles, ceilings, electrical, and plumbing. Regular work hours run Monday to Saturday, 6 am to 10 pm, with occasional Sunday and holiday work and overnight work from 10 pm to 6 am when required. Residents near Great Northern Way and Emily Carr should expect occasional overnight noise.

At Mount Pleasant Station, a November 2 update says crews completed excavation and manhole adjustments on Main Street at East 8th Avenue, from Tuesday November 3 through Friday November 13, with Main Street reduced to two lanes in both directions between Broadway and Kingsway during that period. A June 24 update says Broadway between Quebec and Main streets has been fully restored to four vehicle lanes, and that dynamic testing had been progressing westward past the station at that time.

In the tunnels, crews are working up to 24 hours a day, 7 days a week, installing crew walkways and completing systems.

## What comes next

The Broadway-City Hall Station closure on Broadway between Cambie and Alberta streets is the longest-running single street disruption still in progress. The current work page says that closure will end in January 2027.

The project's current work page notes the Broadway Subway is scheduled to open in 2027. TransLink will operate the line once it opens, connecting riders on the extended Millennium Line to the Canada Line, the Expo Line at Commercial-Broadway, and bus routes across the corridor.

## What residents can do

Residents near a station who hear overnight construction noise can call the 24-hour construction line at 1-844-815-6114. A community information line at 778-572-3544 is open Monday to Friday, 9 am to 5 pm, for less urgent questions. The project posts station-by-station updates at broadwaysubway.ca/construction/current-work/, where new notices appear when the work schedule changes.

Drivers and cyclists planning to cross Broadway between Cambie and Arbutus should check the project's current work page before they travel, as lane patterns and closures continue to shift as each station reaches new construction stages.