title: "Cloverley's final outdoor areas, Highlands addition and three more school projects advance this fall"
description: "North Vancouver's newest school is still working toward its full occupancy permit while four other construction projects are active across School District 44 this fall."
canonical_url: "https://voche.me/bc/north-vancouver-district-2026/news/north-vancouver-school-district-capital-projects-november-2026"
last_updated: "2026-11-17T08:14:54.813Z"
---

Five construction and restoration projects are active across North Vancouver School District this fall, according to a Land Management Update prepared for the board's inaugural meeting on November 17.

The projects range from completing outdoor work at a brand-new school to restoring classrooms after an arson and adding new teaching space at an elementary school that has run out of room.

## Cloverley Elementary: outdoor works, then full occupancy

North Vancouver's first new elementary school in 35 years opened in September 2026 with 370 kindergarten-to-Grade 5 students. The province contributed $61 million toward the project, according to a BC government release, and the district's own newsroom puts the total cost at $64 million. The school was built with mass timber and holds 92 licensed child care spaces operated by North Shore Neighbourhood House.

The building is open and in use, but the full occupancy permit process is not finished. On October 27, the district submitted a revised interim occupancy application to the City of North Vancouver to extend coverage to the bike shelter, sports court and several on-site pathways, according to the board package. Street and site work continues on the west side of the property, including gravel play field, pathways connecting to Hendry Avenue, and the intersection of 5th Street East, Cloverley Street and Shavington Street.

The board package says the project is expected to be complete by the end of November 2026, which will allow the district to apply for the final full occupancy permit.

The school will grow: Grades 6 and 7 are set to be phased in over the next two years, bringing enrolment toward its 585-seat capacity, according to the district's newsroom.

## Dorothy Lynas Elementary: two classrooms left

An arson fire damaged the modular classroom building at Dorothy Lynas Elementary on October 2. Fire restoration work is ongoing, and six of the eight classrooms in the building were restored for occupancy on October 13, according to the board package. The two remaining classrooms are expected to be ready in December.

## Highlands Elementary: modular addition on its way

Highlands Elementary is getting a modular classroom addition. Design development is 50 percent complete, according to the board package. Site service works are expected to begin during the winter school break. Construction of the addition is set to begin over the March break, with the project scheduled for completion in fall 2027.

## Handsworth Secondary: field house washrooms

The District of North Vancouver is building field house washrooms at Handsworth Secondary. The board package says construction is expected to begin in late 2026 and be complete by summer 2027.

## Windsor Secondary: three-phase mechanical upgrade

Windsor Secondary is mid-way through a three-phase mechanical upgrade. Phase 1, the domestic hot water and boiler plant upgrade, started over the summer and is expected to be complete by early December, according to the board package. Phase 2, an air source heat pump installation, will begin after Phase 1. Phase 3, an energy recovery ventilator, will follow Phase 2, subject to budget.

## Lucas Centre: demolition on hold for a tree

The Leo Marshal Curriculum Centre building at the Lucas Centre is scheduled for demolition, but the tender cannot go out yet. The board package says the district is waiting for approval of a tree removal permit for a tree in the building's courtyard. Main gas service rerouting is expected to be complete by the end of November 2026, and the demolition tender package will be posted once that work is done.

## Cheakamus Centre: new fire system in the Longhouse

The Cheakamus Centre is an overnight environmental education facility owned and operated by the district, situated on 165 hectares of ecological reserve near Squamish on traditional Chi'yakmesh territory. It has been in operation since 1969 and includes programs ranging from field school sessions for students to Indigenous cultural programs and educator workshops, according to the centre's own website. Its BlueShore Environmental Learning Centre holds LEED Platinum certification.

A new fire system is being installed in the Longhouse at the centre, with completion expected in January 2027, according to the board package. Modifications to the height of sleeping structures inside the Longhouse have already been completed by Cheakamus staff.

## Blueridge: new accessible playground coming in December

Blueridge Elementary is getting a new accessible playground through the district's Playground Equipment Program. Equipment has been ordered and the project is expected to begin in December, with completion scheduled for early 2027, according to the board package.

## What's next

The next public board meeting is December 15, 2026, at 6:30 pm at the Educational Services Centre at 2121 Lonsdale Avenue, North Vancouver. The public can attend in person or watch through the district's online stream. The next Finance, Audit and Facilities committee meeting is December 1 at 6:00 pm, online.

Residents who want to follow capital projects can check the district's capital project updates page at sd44.ca, and read board packages posted on the public meetings page before each meeting.