title: "Pipeline Road water main work delayed by one year, now expected to finish in early 2028"
description: "Metro Vancouver announced November 24 that Phase 1 of the Coquitlam Water Main project, running along Pipeline Road from Robson Drive to Guildford Way, will finish about a year later than planned after Telus cable conflicts halted work for ten months."
canonical_url: "https://voche.me/bc/coquitlam-2026/news/coquitlam-water-main-pipeline-road-delay-november-2026"
last_updated: "2026-11-26T15:46:48.248Z"
---

Drivers who use Pipeline Road in Coquitlam should plan for continued construction through early 2028, about a year later than originally scheduled, after underground utility conflicts delayed Metro Vancouver's water main project by ten months.

Metro Vancouver announced the revised timeline on November 24, Freshet News reported. [Mayor Craig Hodge](/bc/coquitlam-2026/candidates/craig-hodge) and council were briefed at the November 23 committee meeting, where the city received a second trimester progress report on the project.

## What caused the delay

When the contractor opened Pipeline Road for the new water main, Telus cables were found in a different location than what Metro Vancouver's records showed. The regional agency had to request a redesign from Telus and relocate the cables before work could continue. BC Hydro's underground work in the area was then halted while the cable conflict was being resolved.

Metro Vancouver senior engineer Arezoo Heidarian told Freshet News: "There was a cascading of delays. It took 10 months to resolve the conflict, but it was out of our control."

Telus and BC Hydro have since completed their work along Pipeline Road. As of the announcement, 1,200 of the 1,400 metres of Phase 1 have been installed, Heidarian said.

## The project

The Coquitlam Water Main is a 12-kilometre line running from the northern end of Pipeline Road to Mariner Way at Riverview Crescent. Metro Vancouver has divided the work into four sections: Robson to Guildford, Cape Horn, Pipeline Road North, and a City Centre tunnel. Phase 1, the Robson to Guildford section, spans 1.4 kilometres and the pipe measures 3.2 metres in diameter. Construction on that section started in fall 2023.

The full project runs from 2023 to 2034, according to Metro Vancouver's project page.

## What the city is doing

Jaime Boan, Coquitlam's general manager of engineering and public works, told the committee that city staff maintain weekly contact with Metro Vancouver and are working to keep traffic disruptions and noise as low as possible, Freshet News reported.

Hodge suggested adding more road signage along Pipeline Road to inform commuters about the extended timeline. "The city and Metro Vancouver are taking the heat for third-party issues," Hodge said.

Heidarian declined to disclose the financial impact of the delay. Metro Vancouver said it will update nearby residents through newsletters and meetings, with a community liaison officer collecting feedback. Residents can contact Metro Vancouver by phone at 604-432-6200.

Drivers can check the City of Coquitlam's website at [coquitlam.ca](https://coquitlam.ca) or follow the city on social media for traffic updates on Pipeline Road.